Hopefully from here on in, the process to building our little oasis in Eynesbury will happen smoothly. We're really looking forward to living there! We have met our lovely neighbours, and (via a mutual friend) another family who's land is settling in Sept. Every time we drive out (yes, to admire our empty block!), we congratulate each other on our decision to move to Eynesbury. It's so peaceful and beautiful, we can't wait to live there! Look forward to posting more positive updates, but here's the (kind of disappointing) story so far...
24/08/09 Soil report received
21/09/09 Initial drawings presented by Acquire Designs (via Greybox)
29/09/09 Building contract signed with Greybox
Developer approval received mid-late November
02/12/09 "Final" working drawings presented by Acquire/Greybox, incl. kitchen, bathroom and wardrobe elevations
14/12/09 Building permit issued
21/12/09 Western Water notified Greybox that the sewer point was beneath the garage and had to be relocated
18/01/10 Greybox notified us in writing that the sewer point had to be relocated
04/02/10 Sewer point relocated (subcontracted by Greybox)
05/02/10 Greybox notifies us by phone that the surveying pegs are missing. We go to the block, find two. Greybox asks us to organise the re-establishment survey, which I do.
11/02/10 Block resurveyed by Peter Bennett (great guy, very quick!) Greybox notified in writing 12/02/10.
17/02/10 Western Water issues PIC number (after my phone call to chase them)
01/03/10 Greybox finally responds to our repeated phone calls and emails re: next steps. Says:
...waiting on Joe to confirm everything and get your plans ready to send out, at that point it is then passed onto me and I will then send them out to the suppliers and trades. Your file will be passed onto the supervisor on Wednesday... when I do find out I will pass on their details to you.